WRITTEN BY Alan Bradbury
The stated objective of clause 2.8 is to provide for the temporary use of land if the use does not “compromise future development of the land, or have detrimental economic, social, amenity or environmental effects on the land”.
The clause applies despite any other LEP provisions and allows a consent authority to grant consent for a “temporary use”. A temporary use is one that is carried out for no more than 52 days in any year[1]. The 52 days may be consecutive but do not have to be; for example, a temporary use for the purposes of clause 2.8 could be one that takes place once a week for every week of the year or for a 52 day period once a year.
The 52 day limit does not apply to the temporary use of a dwelling as a sales office for a new release area or a new housing estate[2].
A temporary use can only be approved if the consent authority is satisfied that[3]:
(a) the temporary use will not prejudice the subsequent carrying out of development on the land in accordance with any applicable environmental planning instrument, and
(b) the temporary use will not adversely impact on any adjoining land or the amenity of the neighbourhood, and
(c) the temporary use and location of any structures related to the use will not adversely impact on environmental attributes or features of the land, or increase the risk of natural hazards that may affect the land, and
(d) at the end of the temporary use period the land will, as far as is practicable, be restored to the condition it was in before the use commenced[4].
Clause 2.8 has been the subject of consideration in several decisions of the Land and Environment Court. The principal decisions are:
A number of key principles can be identified in these decisions:
In Marshall’s case, the applicant challenged the validity of development consents granting approval for the temporary use of two barns as a “function centre”. This use was a prohibited use in the relevant rural zone under the Hawkesbury Local Environment Plan 2012. Relevantly, Moore AJ (as he then was) described the nature of the cl 2.8 tests as follows:
[113] The nature of the activities that are capable of being permitted by an application invoking cl 2.8 are, I remind myself, activities that are otherwise prohibited in a zone. [114] That any application that is sought to be approved for such a prohibited use seeks a significant indulgence for such a substantial departure from the planning controls applicable to a zone is reflected in two aspects of the clause. [115] The first arises with respect to the temporal limitation mandated by the clause if such an otherwise prohibited use is to be permitted. This aspect of the clause was the subject of Marshall Rural’s first complaint, a complaint dealt with and dismissed in my rejection of Ground 1. [116] The second element engaged by these proceedings is the requirement that the proposal will “not adversely impact” in the fashion specified in cl 2.8(3)(b). This test, cast in absolute terms reflecting the seriousness with which an application of this nature is required to be assessed, puts a very high hurdle in the path of any such application. The placing of such a hurdle requires that the Council must approach the consideration and determination of any such application with a marked degree of precision and caution.With respect to the ‘temporal limitation’ referred to above at [115] the applicant had argued that cl 2.8 permitted development consent for a maximum period of 12 months from the date of consent. The Court, however, held that the ordinary, obvious reading of cl.2.8 does not impose a second limitation in addition to the number of days in any period of 12 months and that it was open to the consent authority to grant a consent pursuant to cl 2.8 for any nominated limiting period or indeed one that was open-ended.
In relation to the second component, that the proposed development must not adversely impact any adjoining land or the amenity of the neighbourhood, the Court held that the Council had incorrectly proceeded on the basis that it needed to satisfied that the impact of the proposal would be ‘acceptable’ rather than that there would be no adverse impact. His Honour found that the path leading to error began with the acoustic assessment reports which assessed the application by reference to standards which envisaged merely an acceptable impact rather than an absence of adverse impact.
The Court then said that this error had been transmitted to the Council’s own assessment report which, although it referred to cl.2.8(3)(b) on several occasions, did not display a correct understanding of the ‘absolute’ nature of the threshold test imposed by the provision. Moore J was critical of the fact that the assessment report did not caution the councillors that the test imposed by cl.2.8(3)(b) is in absolute terms and was therefore different from the test that is conventionally applied to the assessment of an ordinary development application. In this regard, his Honour explained that the higher threshold reflected the fact that the development for which consent was being sought was otherwise prohibited.
The Court considered that the conditions formulated to address the impact of the proposed development also reflected the same incorrect presumption. Those conditions had sought to require compliance with the remedial acoustic measures recommended by the acoustic experts. However, the Court pointed out that this would merely render the acoustic impact of the proposed development “acceptable” rather than resulting in the removal of any adverse impacts.
This was a Class 1 appeal in relation to the modification of an existing consent for a function centre to extend the period of its operation from one year to three years. The applicant and the Council had participated in a s.34 conciliation conference, as a result of which they had resolved their differences. The owner of a neighbouring property, however, was given leave to intervene in the proceedings to argue that the Court lacked the legal power to approve the development.
The objector argued that the proposed development was prohibited by the Murray Local Environmental Plan 2011. In doing so, he raised 2 contentions. The first was that there was a conflict between cl.2.8 (temporary uses) and another provision which prohibited development on river front areas. The second was that, despite compliance with the restriction on the number of days on which the development would be carried out, the use of the land, on a continuous and regular basis, for the purpose of functions over a three year period could not really be described as a ‘temporary use’.
The Court rejected both arguments.
In relation to the first argument, the Court held that the prohibition of certain development on river front areas was no different to a prohibition in the Land Use Table. Both were subject to cl.2.8. The Court held that a temporary use may occur on land where such a use may otherwise be prohibited provided it meets the requirements of cl.2.8(3). Sheahan J noted that this conclusion was ‘consistent with Moore AJ’s excellent analysis in Marshall’.
In rejecting the second argument, the Court appears to have accepted the applicant’s argument that the prescription of a number of occasions in an identified time period means, in effect, a use which complies with the numerical controls is, by definition, to be regarded as a temporary use. In coming to that conclusion the Court found that the requirement that the land only be used for the specified number of days did not mean that structures to facilitate that use could not be erected and remain on the land throughout the temporary use period. The Court also found that the day limit did not include days on which ancillary activities were carried out, such as the construction and deconstruction of a marquee, inspections, bookings, deliveries and setting up. The days on which those ancillary activities were carried out, were held by the Court not to count in the calculation of the number of days on which the temporary use is carried out.
The content contained in this guide is, of course, general commentary only. It is not legal advice. Readers should contact us and receive our specific advice on the particular situation that concerns them.
Please note that the law detailed in this Essential Guide is correct as at 21 November 2019.
Our series of NSW Local Government Guides are comprehensive yet simple to understand guides on how to deal with certain legislation and problems that NSW Local Government and Councils often face.
[1] Clause 2.8(2); unless another number is adopted in the relevant local environmental plan.
[2] Clause 2.8(4)
[3] Clause 2.8(3)
[4] Unless the temporary use is the use of a dwelling as a sales office for a new release area or a new housing estate see clause 2.8(5)
[5] Provided the 52 day period is the period specified in cl. 2.8(2) and not anther period.
[6] Ibid.